Term I
Week 1 : Identify the nature of project.
Week 2: Sign the dissertation allocation form (14-10-98).
Week 3: Collection of relevant literature and search the Web. The collection of literature
is a continuous activity throughout the project. Feasibility study on collected info.
MwS (21-10-98).
Week 4: Draft requirements specification. MwS (28-10-98).
Week 5: Improve system’s specification. MwS (04-11-98
Week 6: Draft requirements analysis. MwS (11-11-98).
Week 7: Actual requirements analysis. Produce Deliverable I document. MwS (18-11-98).
Week 8: Initial testing strategy. Update Deliverable I. MwS (25-11-9).
Week 9: Meeting with supervisor to discuss the contents of Deliverable I (02-12-98).
Week 10: Finalize Deliverable I. MwS (09-12-98).
Hand-in Deliverable I (11-12-98).ms
Term II
Week 1:Functional Specification. MwS (13/01/99).
Week 2: Functional Design of the system. Produce Data Dictionary.
Interview with Supervisor and 2nd Reader. MwS (20-01-99).
Week 3: Code implementation on identified units of the system.
MwS (27-01-99).
Week 4: Evaluate units. Code is continued. Produce Deliverable II.
MwS (03-02-98).
Week 5: Implementation of system’s functions. MwS (10-02-98.
Week 6: System’s implementation is continued. Perform evaluation in
the implemented code so far. MwS (17-02-99).
Week 7: Code implementation. Revise testing strategy. Update Deliverable II and hand in to supervior.
MwS (24-02-99).
Week 8: Finish the code of the loops part. Produce first draft of Deliverable II MwS (03-03-99).
Week 9: Testing the loops part. Start Functions part.
Meet with Supervisor to discuss upon the Deliverable II.(10-03-99).
Week 10: Code implementation. Finalize Deliverable II. Finalize the code of the Functions part MwS (17-03-99).
ms
Term III
Week 1:
Week 2:
Week 3: Continue coding of the loops part. Start the Web page design
Meet with Supervisor (05-05-99).
Week 4: Finalize the loops part. Start producing final report (Dissertation). MwS (12-05-99).
Week 5: Finalize the control statements and functions part. Work on the Web page as well MwS (19-05-99).
Week 6: Produce first draft of Dissertation and hand-in for feedback. Code on the 'quiz' part. Finalize Web page.
Evaluate system with actual users(26-05-99).
Week 7: Continue evaluation. Analyse results. Finalize dissertation. Meet with Supervisor (02-06-99).
Week 8: Hand-in Dissertation (07-06-99).ms